What government has promised the UK biomethane sector, by when, and whether it has happened. Promises are grouped by policy area and laid out in date order, as Part 1, Part 2 and so on. Each one quotes the official text and links to the source.
15
Promises tracked
2
Delivered
1
Of those, delivered late
3
Overdue now
Next deadline: 1 Dec 2026 - GGSS expenditure forecast statement, 1 December 2026 Jump to it
15 items: 2 delivered, 9 upcoming, 3 overdue, 1 replaced
The subsidy that pays plants for gas they inject. 1 of 7 delivered.
Part 1 of 7
DESNZ - Consultation
“Government is exploring biomethane's optimal role across the energy system and intends to consult on a future biomethane policy framework in FY 2025-26.”
in FY 2025-26 (read as 31 Mar 2026). Source: UK methane action plan - also questions-statements-api.parliament.uk
What happened
17 Jul 2026: The government response on greenhouse gas removals restated work on post-2028 biomethane support, with no new date. Source: Independent review on greenhouse gas removals: government response
Why it matters to plant owners
GGSS Stage 1 takes no new applications after 31 March 2028. Until the successor is consulted on, a plant that misses the GGSS window, or reaches the end of its tariff, has no support design to plan against. Subsidy cliff tracker
Checked 6 Nov 2026
Part 2 of 7
DESNZ - Statutory instrument
“New regulations are expected to come into effect in early 2026 to extend the commissioning window of the Green Gas Support Scheme (GGSS) to 31 March 2030.”
early 2026 (read as 30 Apr 2026). Source: Green Gas Support Scheme (GGSS) - also legislation.gov.uk
What happened
16 Oct 2026: SI 2026/1051 came into force, extending the GGSS commissioning deadline to 31 March 2030 and capping payments for later starters at 31 March 2043. Source: Green Gas Support Scheme (GGSS)
Why it matters to plant owners
Plants commissioning after 31 March 2028 are paid only to 31 March 2043, which is 13 years at the 31 March 2030 deadline, not 15. Stage 1 applications still close on 31 March 2028. GGSS budget and queue
Checked 6 Nov 2026
Part 3 of 7
DESNZ - Statement
“annually by 1 September 2022, 2023, 2024, 2025, 2026 and 2027”
by 1 September 2026 (read as 1 Sept 2026). Source: GOV.UK: GGSS annual tariff reviews and tariff change notices - also ofgem.gov.uk
What happened
Nothing published by 20 Nov 2026.
Why it matters to plant owners
The annual review can change GGSS tariffs and degression thresholds for new applicants from 1 October. Reviews were published each year from 2022 to 2025. GGSS budget and queue
Checked 20 Nov 2026
Part 4 of 7
DESNZ - Statement
“Expenditure Forecast Statements are published by 1 March, 1 June, 1 September and 1 December each year that the GGSS is open to applications. Statements are based on scheme data as of 31 January, 30 April, 31 July and 31 October respectively”
by 1 December (read as 1 Dec 2026). Source: Green Gas Support Scheme (GGSS): expenditure forecast statements and tariff change notices
What happened
Not yet due.
Why it matters to plant owners
The 1 December statement can trigger a 10% cut in GGSS tariffs for new applicants if forecast spend reaches the degression threshold. GGSS budget and queue
Checked 6 Nov 2026
Part 5 of 7
DESNZ - Budget notice
“Budgets will be reviewed annually and announced by 31 December along with the announcement of the Levy rate for the following scheme year.”
by 31 December (read as 31 Dec 2026). Source: Green Gas Support Scheme: budget management - also gov.uk
What happened
Not yet due.
Why it matters to plant owners
Ofgem reports the application budget cap reached and 16 applications queued (as of 5 October 2026). This review is the main route by which queued plants could get a tariff guarantee. GGSS budget and queue
Checked 6 Nov 2026
Part 6 of 7
HM Treasury - Budget notice
“The government will introduce a new comprehensive Cost Control Framework (CCF) at the spending review in 2027 that will set budgets for components of energy costs, including policy costs, to ensure government action drives bills down over the next 10 years. Until that CCF is in place, no further policy costs will be placed on bills unless they bring bills down or are essential for security of supply.”
at the spending review in 2027 (read as 31 Dec 2027). Source: Budget 2026
What happened
Not yet due.
Why it matters to plant owners
The GGSS is paid for by the Green Gas Levy on gas suppliers. InfraValue's reading, not a government statement: until this framework is in place, a bigger GGSS budget for queued plants may be harder to agree. GGSS budget and queue
Checked 6 Nov 2026
Part 7 of 7
Ofgem - Statutory instrument
“The deadline for a stage 1 application is 31 March 2028.”
by 31 March 2028 (read as 31 Mar 2028). Source: Ofgem: Green Gas Support Scheme, information for applicants - also gov.uk
What happened
Not yet due.
Why it matters to plant owners
The last date a new plant can apply for GGSS support. The commissioning deadline is now 31 March 2030, so any plant not in the scheme by this date depends on the successor framework, which has not yet been consulted on. GGSS budget and queue
Checked 20 Nov 2026
The certificate scheme for biomethane sold as road fuel. 0 of 1 delivered.
Single milestone
DfT - Statutory instrument
“Subject to that consultation, and parliamentary time, we aim to introduce any necessary legislation in 2026 and implement any changes to the RTFO in time for the start of the 2027 reporting year.”
legislation in 2026 (read as 31 Dec 2026). Source: RTFO statutory review and the future of the scheme: summary of responses and policy update (section 1.37)
What happened
Not yet due.
Why it matters to plant owners
Rewarding fuels by emissions savings would change the certificates a biomethane plant earns as transport fuel, a main route to market after its subsidy ends. RTFO on GHG savings scenario
Checked 6 Nov 2026
Carbon pricing rules that touch waste and removals. 0 of 1 delivered.
Single milestone
UK ETS Authority - Government response
“The Authority will aim to legislate to integrate removals in the UK ETS by the end of 2028, aiming for integration to be operational by the end of 2029 subject to consideration of appropriate legislative powers, regulatory assessments and further consultation.”
by the end of 2028 (read as 31 Dec 2028). Source: Integrating greenhouse gas removals in the UK Emissions Trading Scheme: main response - also gov.uk
What happened
Not yet due.
Why it matters to plant owners
CO2 captured when biogas is upgraded could earn removal value if it qualifies. This is the earliest a UK carbon market would pay for it. Bio-CO2 scenario
Checked 6 Nov 2026
Rules on food waste collections and digestate. 1 of 3 delivered.
Part 1 of 3
Defra - Government response
“Waste collection authorities will be required to introduce weekly food waste collections to all households in England, including flats, by 31 March 2026 - unless they need longer to transition due to a long-term waste disposal contract”
by 31 March 2026 (read as 31 Mar 2026). Source: Consistency in household and business recycling in England: government response
What happened
31 Mar 2026: The new household recycling rules came into force in England on 31 March 2026. Some councils have "agreed transitional arrangements allowing a later implementation date". Source: Simpler household recycling rules come into force across England
Why it matters to plant owners
More separately collected food waste in England. Food-waste gate fees are an input to waste-fed plant valuations, and more supply tends to push them down. Valuation method
Checked 6 Nov 2026
Part 2 of 3
Defra - Statement
“These rules came into force on 31 March 2025. Micro-firms (with fewer than 10 full-time equivalent employees) have until 31 March 2027.”
until 31 March 2027 (read as 31 Mar 2027). Source: Simpler Recycling: workplace recycling in England
What happened
Not yet due.
Why it matters to plant owners
The last step of England's separate food waste collection rules. It adds commercial food waste supply for waste-fed AD. Valuation method
Checked 6 Nov 2026
Part 3 of 3
UK ETS Authority - Consultation
“...how waste incineration and energy from waste will be included in the scheme from 2026 for the Monitoring, Reporting and Verification (MRV) only period, with full surrender obligations from 2028.”
from 2028 (read as 1 Jan 2028). Source: UK Emissions Trading Scheme scope expansion: waste
What happened
26 Aug 2026: The UK ETS Authority confirmed waste incineration will not join the scheme in 2028 and said a new timeline will follow. Source: UK Emissions Trading Scheme (UK ETS): a policy overview
Why it matters to plant owners
A carbon price on energy-from-waste would raise the cost of the main alternative to AD for food waste and support AD gate fees. The delay removes that support for now. Gate fee scenario
Checked 6 Nov 2026
Environmental permits for anaerobic digestion. 0 of 2 delivered.
Part 1 of 2
Environment Agency - Guidance review
“The Environment Agency will review this resource framework in summer 2026, with support from industry.”
in summer 2026 (read as 31 Aug 2026). Source: Anaerobic digestate resource framework
What happened
Nothing published by 6 Nov 2026.
Why it matters to plant owners
Digestate from source-segregated waste is not waste only if it meets this framework. A tighter framework would add testing or disposal cost for waste-fed plants. Environment Agency permit data
Checked 6 Nov 2026
Part 2 of 2
Defra - Consultation
“We will consult on ensuring non-waste AD is captured as an activity in the EPRs in 2026.”
in 2026 (read as 31 Dec 2026). Source: Industrial emissions: modernising environmental permitting, summary of responses and government response
What happened
Not yet due.
Why it matters to plant owners
Plants that digest only crops or other non-waste feedstocks can sit outside environmental permitting today. Bringing them in would add permit, monitoring and fee costs. Valuation method
Checked 6 Nov 2026
Carbon capture projects linked to biogas. 0 of 1 delivered.
Single milestone
DESNZ - Selection process
“By end of 2026 (indicative) Project Negotiation List (PNL) published”
By end of 2026 (indicative) (read as 31 Dec 2026). Source: CCUS East Coast Cluster NPT Pathfinder: application guidance v1.0 - also gov.uk
What happened
Not yet due.
Why it matters to plant owners
The government's response on removals names this process as a possible route for removals from AD plants far from CO2 pipelines. The list shows whether any biomethane project gets through. Bio-CO2 scenario
Checked 6 Nov 2026
Overdue. The government's own date has passed and we found no publication that delivers it on the owning GOV.UK page or in GOV.UK search.
Parts. Promises are grouped by policy area. Part numbers follow the due date within each area; they are our ordering, not an official one.
Dates. Where the government gave a season or a financial year, we use the last day it could mean.
Quotes. Quotes are word for word; we replace long dashes with hyphens.
Checks. Each item is checked monthly; the date is on the item. Methodology
Sources: GOV.UK (DESNZ, DfT, Defra, HM Treasury, Environment Agency, UK ETS Authority), legislation.gov.uk.